Painting
2019-05-17
Painting plan:
Matching: low alloy carbon steel coating system under severe corrosive environment C5-M
Painting site | Types of | Dry film thickness (μm) | Number of paintings | Total film (μm) |
Ballast tank | Epoxy paint | 125 | X3 | 375 |
Stain tank | Epoxy paint | 150 | X2 | 300 |
Oil tank | Epoxy paint | 150 | X2 | 300 |
other | Epoxy thinner | ---- | ---- | ---- |
Dosage: combined with the estimated area and matching, the estimated dosage is as follows:
Site | Area ㎡ | Total dry film thickness(μm) | Theory (L) | Theoretical set (barrel 20L) | Estimated dosage
L | Estimate the number of sets (according to 20L) |
Ballast tank | 8604 | 375 | 5377.5 | 267 | 10675 | 534 |
Stain tank | 6530 | 300 | 3265.0 | 163 | 6530 | 327 |
Oil tank | 17172 | 300 | 8586.0 | 428 | 17172 | 857 |
Total | 32306 | ----- | 17228.5 | 858 | 34377 | 1718 |
Thinner dosage: 140 barrels (~8%) |
Description:
1. Among them, the painting area is estimated based on the situation investigated by our company.
2. The above estimated consumption loss factor is tentatively set to 2.0. The final data is based on the data provided by the shipowner.
Home· BaoJun· Construction Coating· Industrial Coating· Solution· Project· Service· Intelligent Manufacturing
Address:No. 9 Chuangxin Avenue, Binhai Science and Technology Park, Binhai High-tech Zone, Tianjin,China Zip code:300457
National Hotline
400-022-5055